Project Duration
Stipulated Date of Commencement
January 23 2006
Stipulated Date of Completion /
Likely Date of Completion October 23 2006
Likely Date of Completion October 23 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,700,000.00
Awarded for
₹ 25,218,510.00
Contractors
M/s. Schindler (I) Pvt. Ltd., M/s. Schindler (I) Pvt. Ltd.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD