Project Duration
Stipulated Date of Commencement January 23 2006
Stipulated Date of Completion /
Likely Date of Completion
October 23 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,700,000.00
Awarded for ₹ 25,218,510.00
 
Gallery Image
Contractors
M/s. Schindler (I) Pvt. Ltd., M/s. Schindler (I) Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Construction of Forest Headquarters Building at Altinho Old IPHB Complex -Interior & Furniture works.

View Project
Similar Project

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa

View Project
Similar Project

Restoration of old Government Secretariat Building at Panaji, Goa to make it a Centre of Art and Culture- civil, plumbing & Electrical work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.