Project Duration
Stipulated Date of Commencement
February 26 2018
Stipulated Date of Completion /
Likely Date of Completion April 26 2018
Likely Date of Completion April 26 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,399,120.00
Awarded for
₹ 2,820,440.00

Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.

Consultants
M/s. Madhav Kamat & Associates

See Similar Projects

Construction of footpath from Sai Service junction to training college junction at Porvorim – Electrical works
View Project
Dismantling of HT overhead lines, supplying & laying of HT underground cables at Panaji – Cable work from EDC substation to Chimbel junction.
View Project
Construction of Concrete Pavement Road and other development work from Miramar Circle to NIO Circle and Raj Bhavan
View Project