Project Duration
Stipulated Date of Commencement
March 18 2004
Stipulated Date of Completion /
Likely Date of Completion November 17 2004
Likely Date of Completion November 17 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 100,000,000.00
Awarded for
₹ 79,443,000.00
Project highlights
The Patto Bridge is 200 mts. in length, 12 mts. wide having geometrical features similar to the existing Patto Bridge. The foundations are pile foundations.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. S.N.Bhobe & Associates Pvt. Ltd