Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion November 25 2014
Likely Date of Completion November 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,20,38,902.00
Awarded for
₹ 88,735,464.00
Project highlights
Jetty length of 104 meters constructed to provide facility for Barges, launches, Cruise Operators industry. Designed according to Holistic Design of Panaji like glass railing, Olivio Grande LED fitting . Euipped with cathodic prevention system.
Contractors
M/s. Kargwal Constructions Pvt. Ltd.,
Consultants
M/s. Madhav Kamat & Associates, J
See Similar Projects
Upgradation of the Road connecting Integrated School Complex to NH17 – Civil, Plumbing & Electrical works
View Project
Phase II : Civil & Electrical works
View Project
Development works at Old Goa (Road connecting NH-4A to Miraculous Cross Church).
View Project





