Project Duration
Stipulated Date of Commencement February 26 2014
Stipulated Date of Completion /
Likely Date of Completion
November 25 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,20,38,902.00
Awarded for ₹ 88,735,464.00

Project highlights

Jetty length of 104 meters constructed to provide facility for Barges, launches, Cruise Operators industry. Designed according to Holistic Design of Panaji like glass railing, Olivio Grande LED fitting . Euipped with cathodic prevention system.

 
Gallery Image
Contractors
M/s. Kargwal Constructions Pvt. Ltd.,
Gallery Image
Consultants
M/s. Madhav Kamat & Associates, J
 
Similar Projects

See Similar Projects

Similar Project

Design & Construction of Bridge across river Zuari between Amona and Virdi.

View Project
Similar Project

Rawanfond Bridge

View Project
Similar Project

Comprehensive electrical underground cabling work at Bambolim.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.