Project Duration
Stipulated Date of Commencement
January 28 2019
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 244,635,361.96
Awarded for
₹ 257,346,957.63
Project highlights
Construction of State of the Art Higher Secondary School Under Phase I.
Contractors
M/s. Parnika Commercial & Estates P. Ltd
Consultants
M/s. KICONS Limited