Project Duration
Stipulated Date of Commencement
October 30 2011
Actual Date of Completion
September 04 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,493,415.00
Awarded for
₹ 5,399,824.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Electrical work.
View ProjectSupply, installation, testing & commissioning of portable OT light.
View ProjectSupply, Installation, Testing and Commissioning of Heart Lung machine
View Project