Project Duration
Stipulated Date of Commencement
December 25 2010
Actual Date of Completion
September 07 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,13,89,800.00
Awarded for
₹ 2,08,76,500.00
Contractors
M/s. MGI (India) Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.