Project Duration
Stipulated Date of Commencement December 25 2010
Actual Date of Completion September 07 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,13,89,800.00
Awarded for ₹ 2,08,76,500.00
 
Contractors
M/s. MGI (India) Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 

See Similar Projects

Construction of building with compound wall for 30 bedded hospital at Bicholim – Civil, Plumbing & Electrical works.

View Project

Mortuary Cabinet.

View Project

Electrical works (External)

View Project
x