Project Duration
Stipulated Date of Commencement
April 09 2011
Actual Date of Completion
October 05 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,476,337.00
Awarded for
₹ 6,651,820.00
Contractors
M/s. MDD Medical Systems (India) Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.