Project Duration
Start Date 03/03/2007
End Date 19/12/2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 174,969,028.00
Awarded for ₹ 186,209,408.98
Final Cost of Project ₹ 477,277,039.00

Project highlights

RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.

 
Contractors
M/s. IVRCL Infrastructures & Projects Limited
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 

See Similar Projects

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Lecture Hall Elevator and Girls Hostel Elevator installed at Goa Medical College and Hospital, Bambolim for three years (2018-2021).

View Project

External Electrical work

View Project

Construction of Multi Purpose Community Hall for Department of Tribal Welfare at Harvalem Sankhali, Bicholim Taluka

View Project
x