Project highlights
- RCC five storeyed building.
- Ground Floor : Casualty ward & morgue, O.T.
- First Floor : Consulting rooms.
- Second Floor : Surgical wards, OT (04 nos.), ICU.
- Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
- Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.

Contractors

Consultants
Additional Work
This project involved 14 additional tasks. The details of the same available below
Status | Progress | Project Duration Start Date / End Date |
Cost (Rs.) Estimated / Awarded |
Consultants & Contractors | ||
---|---|---|---|---|---|---|
|
||||||
100% completed
|
01/05/2008 - 13/09/2012 |
₹ 17,230,000.00 / ₹ 17,000,000.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd. - |
|||
|
||||||
100% completed
|
18/08/2009 - 30/11/2012 |
₹ 61,06,052.00 / ₹ 7,020,395.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Japsin Jacob Wire Drawing Pvt. Ltd. - |
|||
|
||||||
100% completed
|
19/12/2009 - 30/09/2012 |
₹ 37,738,817.00 / ₹ 37,340,650.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Vigneshwar Air Conditioning Pvt. Ltd. - |
|||
|
||||||
100% completed
|
19/12/2009 - 30/09/2012 |
₹ 20,042,857.00 / ₹ 14,820,456.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Imperial Engineering Company - |
|||
|
||||||
100% completed
|
19/02/2010 - 17/08/2012 |
₹ 14,076,253.00 / ₹ 13,168,155.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Imperial Engineering Company - |
|||
|
||||||
100% completed
|
14/09/2010 - 19/12/2012 |
₹ 24,341,483.24 / ₹ 18,900,000.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Knchan Associates - |
|||
|
||||||
100% completed
|
25/12/2010 - 07/09/2012 |
₹ 2,13,89,800.00 / ₹ 2,08,76,500.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. MGI (India) Pvt. Ltd. - |
|||
|
||||||
100% completed
|
09/04/2011 - 05/10/2012 |
₹ 5,476,337.00 / ₹ 6,651,820.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. MDD Medical Systems (India) Pvt. Ltd. - |
|||
|
||||||
100% completed
|
30/10/2011 - 04/09/2012 |
₹ 7,493,415.00 / ₹ 5,399,824.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Siemens Enterprises Communications Pvt. Ltd. - |
|||
|
||||||
100% completed
|
07/11/2011 - 05/10/2012 |
₹ 1,54,15,844.00 (corrected) / ₹ 17,629,974.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Imperial Engineering Company - |
|||
|
||||||
100% completed
|
21/10/2011 - 20/12/2011 |
₹ 1,231,241.00 / ₹ 1,446,000.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Megastar Engineering - |
|||
|
||||||
100% completed
|
02/01/2012 - 19/12/2012 |
₹ 3.00 / ₹ 27,034,799.66 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Concept Creator - |
|||
|
||||||
100% completed
|
09/10/2012 - 19/12/2012 |
₹ 2,923,512.21 / ₹ 3,083,239.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Vrindanvan Agricultural Services - |
|||
|
||||||
100% completed
|
03/03/2007 - 19/12/2012 |
₹ 174,969,028.00 / ₹ 186,209,408.98 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. IVRCL Infrastructures & Projects Limited - |
|||

See Similar Projects

Construction of Forensic Block and Morgue for Goa Medical College at Bambolim’
View Project
Rural Medical Dispensary at Keri.
View Project
Restoration and Adaptive re-use of Old GMC.
View Project