Project Duration
Stipulated Date of Commencement February 26 2015
Stipulated Date of Completion /
Likely Date of Completion
August 25 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,97,09,697.00
Awarded for ₹ 21,19,74,093.00

Project highlights

Demolition and Construction of 20bedded Hospital which is G+2 building and Hostel with 18rooms of double occupancy, G+1 building.The hospital provides Administrative office, Pharmacy, OPDs, Immunization room, Casualty, Dressing room, Post natal, Labor room, male/female toilets, Ward sister’s room, Seminar hall, Male/Female ward, Sterilization room, Minor OT, changing/ rest rooms, Examination room. The hostel is also provided with office, mess facility with kitchen and dining hall, servant’s room, library room, recreation room, etc.

 
Gallery Image
Contractors
M/s. S.N. Constructions
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Supply, Testing and Commissioning of Ventilators with Humidifiers

View Project
Similar Project

Major Maintenance Work of Goa Medical College & Hospital at Bambolim, Goa SH : Operation & maintenance contract for Centralized Air Conditioning (AC) system of GMC at Bambolim, Goa for 3 years (2020-2023)

View Project
Similar Project

Supply, Installation, Testing and Commissioning of E. T. O Machine

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.