Project Duration
Stipulated Date of Commencement
May 16 2014
Stipulated Date of Completion /
Likely Date of Completion June 15 2014
Likely Date of Completion June 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 445,576.00
Awarded for
₹ 521,000.00
Project highlights
Electrical Works
Contractors
M/s.Desai Electrical & Electronics Sales & Services
Consultants
In-house (GSIDC)
See Similar Projects
Construction of compound wall at Calangute / Saligao in North Goa.
View Project
Erection, testing and commissioning of Air Conditioned Hanger at Dayanad Bandodkar Football Ground, Campal, Panaji, Goa for IFFI 2012.
View Project
Construction of RCC sump and pumping system.
View Project