Status
100%
Completed
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of subway at Bambolim – Civil works
100% completed
Project Duration
Stipulated Date of Commencement
February 11 2007
Stipulated Date of Completion /
Likely Date of Completion January 25 2009
Likely Date of Completion January 25 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 51,241,559.00
Awarded for
₹ 71,828,955.90
Final Cost of Project
₹ 71,288,337.00
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd., M/s. Mahimtura Consultants Pvt. Ltd.
2
Electrical works
100% completed
Project Duration
Stipulated Date of Commencement
October 14 2008
Stipulated Date of Completion /
Likely Date of Completion January 25 2009
Likely Date of Completion January 25 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,000,480.00
Awarded for
₹ 1,847,925.00
Contractors
M/s James Electricals
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
See Similar Projects
Conversion of Pedestrian Subway to Motorable Subway at Bambolim, Goa – Civil, Plumbing & Electrical works
View ProjectHotmixing of Road from Sai Service Junction to Training College Junction at Porvorim, Goa
View ProjectConstruction of Bus Stand and Shopping Complex at Assonora
View Project