Project Duration
Stipulated Date of Commencement
November 26 2022
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 4,256,245.71
Awarded for
₹ 3,833,821.79
Project highlights
Setting up STP and its Electromechanical work
Contractors
M/s. Samco Water Technologies
Consultants
M/s. FP Project Management