Project Duration
Stipulated Date of Commencement
October 08 2014
Stipulated Date of Completion /
Likely Date of Completion July 07 2015
Likely Date of Completion July 07 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 25,327,511.89
Awarded for
₹ 31,757,401.92
Project highlights
New community hall to cater to needs of the local villagers to hold functions and gatherings personal / public
Contractors
M/s. S. M. Realtors,
Consultants
M/s. Murty & Manyam,