Project Duration
Stipulated Date of Commencement
September 04 2009
Actual Date of Completion
November 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,013,381.00
Awarded for
₹ 19,163,609.00
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.