Project Duration
Stipulated Date of Commencement March 21 2013
Actual Date of Completion January 16 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 16,532,155.00
Awarded for ₹ 14,482,150.00
 
Contractors
M/s. Modern Stage Services
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 