Project Duration
End Date 30/11/2013
Status
100%
Completed
Final Cost of Project ₹ 446418072.00

Project highlights

  • Triple purpose Auditorium having 800 seating capacity : Can be used for performing arts, movies, and also for seminars.
  • Provision of Open Air Theatre.
  • Main auditorium building mainly comprises of main auditorium, projector room, entrance lobby, holding area, reception, ticketing counters, conference room, rooms for Chairman, Vice Chairman & Member Secretary, Green rooms, Cry room, snack area, exhibition area, spaces corridor and staircases  along with ample storage space, toilets blocks.
  • Open Air Theatre mainly comprising stage, seating arrangements, control room, green rooms along with ample storage space, toilets blocks.
  • Training and Dormitory mainly comprises of reception, Gents and ladies Dormitory, Administrative room, training, room pantry, VIP suite and Actor rooms with ample storage and toilets.
 
Contractors
M/s. M. Venkata Rao Infra Projects Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 

Additional Work

This project involved 15 additional tasks. The details of the same available below

Status Progress Project Duration
Start Date / End Date
Cost (Rs.)
Estimated / Awarded
Consultants & Contractors
1 Acoustic work.
100% completed
 
 

19/02/2010 - 30/10/2013

 

₹ 49,680,288.00 / ₹ 46,380,920.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Indecor Slides (I) Pvt. Ltd. -
2 Interior works.
100% completed
 
 

11/02/2010 - 15/11/2013

 

₹ 11,877,563.00 / ₹ 9,939,420.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Knchan Associates -
3 Air conditioning & ventilation system.
100% completed
 
 

04/09/2009 - 30/11/2013

 

₹ 19,013,381.00 / ₹ 19,163,609.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Vigneshwar Air Conditioning Pvt. Ltd. -
4 External Electrical works.
100% completed
 
 

04/09/2009 - 30/11/2013

 

₹ 27,245,405.00 / ₹ 23,666,666.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd. -
5 Fire Fighting, Fire Alarm, CCTV and PA System.
100% completed
 
 

24/02/2010 -

 

₹ 6,364,774.00 / ₹ 6,037,795.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Consolidated Construction Consortium Ltd. -
6 Additional civil work.
100% completed
 
 

15/12/2011 - 30/11/2013

 

₹ 50,839,145.00 / ₹ 54,866,128.92

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. M. Venkata Rao Infra Projects Pvt. Ltd. -
7 Stage craft
100% completed
 
 

17/02/2013 - 13/02/2014

 

₹ 15,378,922.00 / ₹ 9,380,500.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Pandurang Kothare -
8 Stage lighting
100% completed
 
 

21/03/2013 - 1/16/2014

 

₹ 16,532,155.00 / ₹ 14,482,150.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Modern Stage Services -
9 Audio video
100% completed
 
 

27/01/2013 - 6/20/2014

 

₹ 33,774,924.00 / ₹ 27,041,231.40

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. AGC Networks Ltd. -
10 Tiling work.
100% completed
 
 

07/03/2013 - 31/07/2013

 

₹ - / ₹ 1,772,037.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Indage Development Construction Pvt. Ltd. -
11 Landscaping work
100% completed
 
 

18/03/2013 - 15/12/2013

 

₹ 5,589,444.00 / ₹ 5,511,513.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. Gurudatta Gardners & Developers -
12 Construction of Ravindra Bhavan at Sanquelim, Goa – CCTV & other works.
100% completed
 
 

06/08/2015 - 04/01/2016

 

₹ 5,377,520.00 / ₹ 5,745,270.95

  Inhouse
M/s. Psytech Infosolutions Pvt. Ltd. -
13 Testing & Commissioning of the fire Fighting, Fire Alarm and PA System
100% completed
 
 

28/02/2014 - 3/29/2014

 

₹ 411,040.00 / ₹ 388,200.00

  Inhouse
M/s.Psytech Infosolutions (India) Pvt. Ltd. -
14 Additional Fire fighting work
100% completed
 
 

8/19/2014 - 9/19/2014

 

₹ 1,159,205.60 / ₹ 1,204,885.57

  Inhouse
M/s.Psytech Infosolutions (India) Pvt. Ltd. -
15 Construction of Ravindra Bhavan at Sanquelim, Goa -Phase I : Civil, plumbing, land development, electrical (part)
100% completed
 
 

02/03/2007 - 30/11/2013

 

₹ 107,796,055.00 / ₹ 134,010,749.00

  M/s. Intertek Architects & Consultants Pvt. Ltd.
M/s. M. Venkata Rao Infra Projects Pvt. Ltd. -

See Similar Projects

Construction of market at Nuvem.

View Project

Upgradation of Infrastructure in the Rural Areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme, 2013 – Construction of Panchayat Ghar and Market Complex at VP Cotorem.

View Project

Package II (VP Siridao, VP Goa Velha, VP Curca).

View Project
x