Project highlights
Triple purpose Auditorium having 800 seating capacity : Can be used for performing arts, movies, and also for seminars.
Provision of Open Air Theatre.
Main auditorium building mainly comprises of main auditorium, projector room, entrance lobby, holding area, reception, ticketing counters, conference room, rooms for Chairman, Vice Chairman & Member Secretary, Green rooms, Cry room, snack area, exhibition area, spaces corridor and staircases along with ample storage space, toilets blocks.
Open Air Theatre mainly comprising stage, seating arrangements, control room, green rooms along with ample storage space, toilets blocks.
Training and Dormitory mainly comprises of reception, Gents and ladies Dormitory, Administrative room, training, room pantry, VIP suite and Actor rooms with ample storage and toilets.

Contractors

Consultants
Additional Work
This project involved 15 additional tasks. The details of the same available below
Status | Progress | Project Duration Stipulated Date of Commencement / Stipulated Date of Completion/Likely Date of Completion |
Cost (Rs.) Estimated / Awarded |
Consultants & Contractors | ||
---|---|---|---|---|---|---|
|
||||||
100% completed
|
19/2/2010 - 30/10/2013 |
₹ 49,680,288.00 / ₹ 46,380,920.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Indecor Slides (I) Pvt. Ltd. |
|||
|
||||||
100% completed
|
11/2/2010 - 15/11/2013 |
₹ 11,877,563.00 / ₹ 9,939,420.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Knchan Associates |
|||
|
||||||
100% completed
|
4/9/2009 - 30/11/2013 |
₹ 19,013,381.00 / ₹ 19,163,609.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Vigneshwar Air Conditioning Pvt. Ltd. |
|||
|
||||||
100% completed
|
4/9/2009 - 30/11/2013 |
₹ 27,245,405.00 / ₹ 23,666,666.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd. |
|||
|
||||||
100% completed
|
24/2/2010 - |
₹ 6,364,774.00 / ₹ 6,037,795.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Consolidated Construction Consortium Ltd. |
|||
|
||||||
100% completed
|
15/12/2011 - 30/11/2013 |
₹ 50,839,145.00 / ₹ 54,866,128.92 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. M. Venkata Rao Infra Projects Pvt. Ltd. |
|||
|
||||||
100% completed
|
17/2/2013 - 13/2/2014 |
₹ 15,378,922.00 / ₹ 9,380,500.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Pandurang Kothare |
|||
|
||||||
100% completed
|
21/3/2013 - 1/16/2014 |
₹ 16,532,155.00 / ₹ 14,482,150.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Modern Stage Services |
|||
|
||||||
100% completed
|
27/1/2013 - 6/20/2014 |
₹ 33,774,924.00 / ₹ 27,041,231.40 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. AGC Networks Ltd. |
|||
|
||||||
100% completed
|
7/3/2013 - 31/7/2013 |
₹ - / ₹ 1,772,037.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Indage Development Construction Pvt. Ltd. |
|||
|
||||||
100% completed
|
18/3/2013 - 15/12/2013 |
₹ 5,589,444.00 / ₹ 5,511,513.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. Gurudatta Gardners & Developers |
|||
|
||||||
100% completed
|
6/8/2015 - 4/1/2016 |
₹ 5,377,520.00 / ₹ 5,745,270.95 |
Inhouse
- M/s. Psytech Infosolutions Pvt. Ltd. |
|||
|
||||||
100% completed
|
28/2/2014 - 3/29/2014 |
₹ 411,040.00 / ₹ 388,200.00 |
Inhouse
- M/s.Psytech Infosolutions (India) Pvt. Ltd. |
|||
|
||||||
100% completed
|
8/19/2014 - 9/19/2014 |
₹ 1,159,205.60 / ₹ 1,204,885.57 |
Inhouse
- M/s.Psytech Infosolutions (India) Pvt. Ltd. |
|||
|
||||||
100% completed
|
2/3/2007 - 30/11/2013 |
₹ 107,796,055.00 / ₹ 134,010,749.00 |
M/s. Intertek Architects & Consultants Pvt. Ltd., M/s. Intertek Architects & Consultants Pvt. Ltd.
- M/s. M. Venkata Rao Infra Projects Pvt. Ltd. |
|||