Project Duration
Stipulated Date of Commencement
February 04 2024
Stipulated Date of Completion /
Likely Date of Completion July 27 2024
Likely Date of Completion July 27 2024
Status
80%
Completed
Cost (₹)
Estimated at
₹ 22,407,116.00
Awarded for
₹ 14,063,310.00
Project highlights
Providing & Installation of Audio Video Equipment for Ravindra Bhavan Auditorium.
Contractors
M/s. Unicom Infotel Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment