Status
100%
Completed

Project highlights

An RCC framed G+3 auditorium building which consists of a centrally air conditioned auditorium with a capacity of 768 seats (591 seats in ground floor and 177 seats in balcony)., Green rooms, Rehersal rooms, a mini theatre with a capacity of 170 seats, toilets for ladies , gents and handicapped on each floor, Set storage room ect. and the related facilities like a G+2 Canteen building having administrative area at ground floor, canteen on the first floor and Ladies and gents dormitory and three guest rooms on the second floor.

 
Contractors
Consultants
 

Sub Works

This project involved 17 sub works. The details of the same available below

1

Civil and Plumbing works.

100% completed
 
Project Duration
Stipulated Date of Commencement October 29 2008
Stipulated Date of Completion /
Likely Date of Completion
June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 133,955,490.42
Awarded for ₹ 211,937,309.40
Final Cost of Project ₹ 371,334,070.00
 
Contractors
M/s.Silpa Projects and Infrastructure (I) Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.,
2

Elevator work

100% completed
 
Project Duration
Stipulated Date of Commencement December 25 2010
Stipulated Date of Completion /
Likely Date of Completion
June 07 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 55,35,000.00
Awarded for ₹ 6,420,000.00
 
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
3

Internal & External Electrical work.

100% completed
 
Project Duration
Stipulated Date of Commencement December 25 2010
Stipulated Date of Completion /
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,61,21,471.00
Awarded for ₹ 13,418,362.92
 
Contractors
M/s. Power & Instrumentation (Guj) Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
4

Fire fighting, fire alarm and PA System

100% completed
 
Project Duration
Stipulated Date of Commencement April 26 2011
Stipulated Date of Completion /
Likely Date of Completion
November 13 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,373,990.00
Awarded for ₹ 12,323,666.60
 
Contractors
M/s. Fire Remedy Systems
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
5

Interiors (Part I)

100% completed
 
Project Duration
Stipulated Date of Commencement April 30 2012
Stipulated Date of Completion /
Likely Date of Completion
May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 52,151,492.00
Awarded for ₹ 4,98,51,017.15

Project highlights

Interior Works for Ravindra Bhavan at Baina.

 
Contractors
M/s. T. S. Mistry
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
6

HVAC work.

100% completed
 
Project Duration
Stipulated Date of Commencement June 01 2012
Stipulated Date of Completion /
Likely Date of Completion
July 25 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 28,513,151.55
Awarded for ₹ 34,663,132.43
 
Contractors
M/s. IDMC Limited
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
7

Audio visual work

100% completed
 
Project Duration
Stipulated Date of Commencement May 21 2012
Stipulated Date of Completion /
Likely Date of Completion
November 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,737,760.00
Awarded for ₹ 16,462,076.00
 
Contractors
M/s. AGC Networks Limited
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
8

Structural works in Auditorium

100% completed
 
Project Duration
Stipulated Date of Commencement June 12 2012
Stipulated Date of Completion /
Likely Date of Completion
May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,839,786.00
Awarded for ₹ 6,220,033.00

Project highlights

Providing of structural work like catwalk, in the building

 
Contractors
M/s. T. S. Mistry
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
9

Loose Furniture Works

100% completed
 
Project Duration
Stipulated Date of Commencement December 20 2012
Stipulated Date of Completion /
Likely Date of Completion
June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 16,979,866.00
Awarded for ₹ 16,540,030.00

Project highlights

Providing of furniture for Office, Canteen, Auditorium, Guest room, Green rooms etc.

 
Contractors
M/s. Concept Creator
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
10

CCTV works

100% completed
 
Project Duration
Stipulated Date of Commencement March 25 2013
Stipulated Date of Completion /
Likely Date of Completion
May 24 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,322,882.00
Awarded for ₹ 1,298,711.00
 
Contractors
M/s. Reconnoitre systems.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
11

Stage Lighting work

100% completed
 
Project Duration
Stipulated Date of Commencement March 15 2013
Stipulated Date of Completion /
Likely Date of Completion
June 14 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,324,376.63
Awarded for ₹ 7,672,481.00
 
Contractors
M/s. Canara Lighting Industries Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
12

Stage Drapery work

100% completed
 
Project Duration
Stipulated Date of Commencement March 25 2013
Stipulated Date of Completion /
Likely Date of Completion
August 12 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,239,800.00
Awarded for ₹ 5,887,500.00
 
Contractors
M/s. Modern Stage Service
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
13

Additional Electrical work

100% completed
 
Project Duration
Stipulated Date of Commencement April 19 2013
Stipulated Date of Completion /
Likely Date of Completion
January 20 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,655,969.78
Awarded for ₹ 2,467,550.00
 
Contractors
M/s. Arken Solutions Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
14

Landscaping work

100% completed
 
Project Duration
Stipulated Date of Commencement March 30 2013
Stipulated Date of Completion /
Likely Date of Completion
May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,728,163.00
Awarded for ₹ 1,946,075.00

Project highlights

Providing of lawn and different types of plants around Ravindra Bhavan.

 
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
15

Signages work

100% completed
 
Project Duration
Stipulated Date of Commencement April 14 2013
Stipulated Date of Completion /
Likely Date of Completion
May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,534,470.00
Awarded for ₹ 2,038,389.00

Project highlights

All types of Signages works.

 
Contractors
M/s. Sai Shilp
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
16

Additional Electrical work (Package 2)

100% completed
 
Project Duration
Stipulated Date of Commencement October 25 2013
Stipulated Date of Completion /
Likely Date of Completion
December 08 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,873,194.00
Awarded for ₹ 5,696,228.64
 
Contractors
M/s. Power & Instrumentation (Guj.) Ltd.
Consultants
Inhouse
17

Additional HVAC work.

100% completed
 
Project Duration
Stipulated Date of Commencement November 12 2014
Stipulated Date of Completion /
Likely Date of Completion
June 30 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,582,490.00
Awarded for ₹ 4,199,999.00
 
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Inhouse

See Similar Projects

Digital Multifunctional Copiers

View Project

750 KVA Diesel Generator work

View Project

Civil and Plumbing works.

View Project