Project Duration
Stipulated Date of Commencement May 01 2008
Actual Date of Completion June 30 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 25,895,502.00
Awarded for ₹ 38,898,833.00
Final Cost of Project ₹ 25,731,965.00

Project highlights

? Length of the bridge is 62 m.
? Carriageway of the bridge is 7.5 m with 1 m footpath on one side.
? Superstructure consists of RCC deck.
? Bridge comprises of 7 piers and 2 abutments.
? Length of approach roads is 93.50 m in the North and 63.00 m in the South with adequate lighting and proper drainage system.

 
Contractors
M/s. Aditya Construction Company, M/s. Aditya Construction Company
Consultants
M/s. Keni & D’Souza, M/s. Keni & D’Souza
 

See Similar Projects

Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.

View Project

Design and Construction of Grade Separator at Dabolim Airport.

View Project

Construction of Bypass road for mining traffic from Uguem to Capxem: Phase I-Uguem to Guddemol, Phase II-Guddemol to Capxem.

View Project
x