Project Duration
Stipulated Date of Commencement August 26 2016
Stipulated Date of Completion /
Likely Date of Completion
November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,051,673.00
Awarded for ₹ 14,133,458.98

Project highlights

(1) Ground floor consists of 1 nos. of shop of size 2.35 x 4.54.mt
(2) First floor consists of Panchayat Office, seperate Talathis Office, Sarpanch , Secretary and Conference room, Animal Husbandary & Electricity Dept and seperate toilets.

 
Gallery Image
Contractors
M/s.Vaishnavi Infrastructure
Gallery Image
Consultants
M/s. Creative Abode
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of facilities of Pilgrims for Exposition 2014 at Old Goa – Internal works.

View Project
Similar Project

Construction of Multiplex.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Audio, Video and CCTV Surveillance System for District Library at Navelim, Margao.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.