Project Duration
Stipulated Date of Commencement March 08 2019
Stipulated Date of Completion /
Likely Date of Completion
September 07 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 13,817,056.68
Awarded for ₹ 15,736,138.28

Project highlights

Structural roofing work for IT Hub

 
Gallery Image
Contractors
M/s. H. Candolkar & Sons
Gallery Image
Consultants
M/s. KICONS Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Lab Accessories work.

View Project
Similar Project

Urgent repairs of the existing lift in the building Essar Trade Centre, Morod, Mapusa, Bardez-Goa, wherein the office of Sub-registrar is situated

View Project
Similar Project

Construction of building at Patto with provision for Gas insulated substation Panaji Phase I

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.