Project Duration
Stipulated Date of Commencement
July 23 2022
Stipulated Date of Completion /
Likely Date of Completion November 22 2023
Likely Date of Completion November 22 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 53,144,732.00
Awarded for
₹ 48,488,436.44
Project highlights
The new building for Directorate of Accounts with a plot area of 5300 sq.m. is a (G+3) Office building with 22 nos. various administrative sections. It also houses a Training hall for 340 pax, Canteen, Bank, ATM and Basement for 75 nos. Car & 45 nos. two wheeler parking.
Contractors
M/s. Mannu Lal & Sons
Consultants
M/s UCJ Architecture & Environment
See Similar Projects
Supply of Adult folding wheel chair for pilgrims for Exposition 2014 at Old Goa.
View Project
Restoration of old Government Secretariat Building at Panaji, Goa to make it a Centre of Art and Culture- civil, plumbing & Electrical work
View Project
Construction of compound wall for Biomedical waste treatement facility at Kundaim.
View Project