Project Duration
Stipulated Date of Commencement
January 17 2022
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 10,824,992.64
Awarded for
₹ 9,125,700.00
Project highlights
Hospital furniture works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. KICONS Limited
See Similar Projects
Construction of IInd phase of Goa Dental College and Hospital at Bambolim, Goa – Furniture, Interior & miscellaneous works – Additional works.
View Project
Construction of Primary Health Centre at Candolim-Goa – – Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting work.
View Project
Upgradation of existing Rural Medical Centre at Collem, Dharbandora – Civil, Plumbing, Electrical, Lift, HVAC and Fire Fighting works
View Project





