Project Duration
Stipulated Date of Commencement
June 26 2023
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
70%
Completed
Cost (₹)
Estimated at
₹ 5,232,093.87
Awarded for
₹ 4,843,757.08
Project highlights
HVAC works.
Contractors
M/s Shree Manguirish Air Conditioning Co.
Consultants
M/s. KICONS Limited