The existing building has been upgraded and will be used as administrative building in future. The new building is being constructed to cater to 70 beds as against 30 beds available earlier.

Project Duration
Start Date Sep 13 2014
End Date Dec 31 2018
Status As on Jul 16 2018
72%
Completed
 

flooring, masonry, door fixing, electrical and HVAC works are in progress.

Cost (Rs.)
Estimated at 44,20,42,846.00
Awarded for 49,73,93,786.00

Construction of 70 bedded hospital, G+1 structure with basement for parking.

 

Project highlights

• Total built-up area of the building is 11,546.82 sq. m.
• Ground + 1 structure with a basement.
• Basement Floor houses the mortuary, workshop, hospital store, laundry, service area and parking for 2 ambulance, 1 mortuary van, 130 nos. cars, 185 two-wheelers.
• Ground Floor houses the OPD, blood bank, CSSD area, casualty, canteen, radiology department, pharmacy, entrance lobby (registration), staff changing area, day care ward, physiotherapy department, community services, service areas, pathology department and toilet blocks.
• First Floor houses the male / female wards, dialysis, O. T., I.C.U, delivery suite, private / semi-private rooms, pediatric ward, maternity ward, NICU, reception / waiting areas, service areas and toilet blocks.

Location

Construction of New Premises for Community Health Centre at Tuem, Pernem Goa -Civil, Plumbing, Electrical, Firefighting, Lift & HVAC works.
Taluka: Pernem
 
Contractors

M/s. Rajdeep Buildcon Pvt. Ltd.

Consultants

M/s. KICONS Limited

Project Incharge

Dilip Joshi

9011066777

Sudesh Sangodkar

9850470849

Nitha Gopi

9011025916
 

Additional Work

This project involved 2 additional tasks. The details of the same available below

Status Progress Project Duration
Start Date / End Date
Cost (Rs.)
Estimated / Awarded
Final Cost of Project
Consultants & Contractors
1 Phase I: Repair and upgradation works of existing community health centre under NRHM.
As on Aug 31 2015

Work completed

As on Aug 31 2015
100% completed
 
 

Aug 26 2013 - Nov 15 2014

 

29996583.00 / 36599357.37

 

M/s. KICONS Limited

M/s. Indage Development Construction Pvt. Ltd

Project Incharge:

Shri. Dilip Srinivas Joshi : 9011066777; Shri. Sudesh J. Sangodkar : 9850470849; Ms. Nitha Gopi : 9011025916

2 Construction of new premises of CHC at Tuem, Pernem- Civil, Plumbing, electrical, lift firefighting , HVAC & Lift works
As on Jul 16 2016

flooring, masonry, door fixing, electrical and HVAC works are in progress.

As on Jul 16 2016
72% completed
 
 

Sep 13 2014 - Dec 31 2018

 

442042846.00 / 497393786.00

 

M/s. KICONS Limited

M/s. Rajdeep Buildcon Pvt. Ltd.

Project Incharge:

Shri. Dilip Srinivas Joshi : 9011066777; Shri. Sudesh J. Sangodkar : 9850470849; Ms. Nitha Gopi : 9011025916

See Similar Projects

Construction of District Hospital at Mapusa, Goa – Civil, Electrical and Plumbing Works

View Project

Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim – Goa-SH-Supply, Installation, Testing and Commissioning of Ventilators

View Project

Upgradation and extension of existing Cottage Hospital at Chicalim, Goa.

View Project
x