Project Duration
Stipulated Date of Commencement
February 10 2024
Stipulated Date of Completion /
Likely Date of Completion July 15 2024
Likely Date of Completion July 15 2024
Status
60%
Completed
Cost (₹)
Estimated at
₹ 2,963,184.00
Awarded for
₹ 3,799,448.83
Project highlights
Modern Anganwadi Centre for children with play area, kitchen, store room, toilet and all finishing works.
Contractors
M/s. Sirajuddin Beig
Consultants
M/s Bhaskar Wagle & Associates