Project Duration
Stipulated Date of Commencement
March 12 2023
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 54,632,130.14
Awarded for
₹ 49,269,330.17
Project highlights
Setting up 11 KV Substation for IPHB Campus at Bambolim.
Contractors
M/s. Imperial Engineering Company
Consultants
M/s. FP Project Management