Project Duration
Stipulated Date of Commencement January 07 2022
Stipulated Date of Completion /
Likely Date of Completion
July 15 2024
Status
99%
Completed
Cost (₹)
Estimated at ₹ 176,805,244.00
Awarded for ₹ 189,521,822.60

Project highlights

Proposed Bridge is two lane (2 nos) with footpath on either side. Bridge consists of 60m x 1 span(Tub girder composite steel concrete superstructure). Foundation-Pile foundation of 1.2m dia & length 30m are proposed. Pile foundation will be in M40 concrete with 8mm liners. Pile caps will be supported on piles. Substructure comprises of RCC plate piers, RCC pier cap with pier pedestals. Grade of concrete shall be M40. Length of Approache roads : Curchorem side – 106.25m & Hodar Side – 90m

 
Gallery Image
Contractors
M/s. K.V.J. Builders and Developers Pvt. Ltd.
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Design and construction of bridge connecting Keri to Tiracol

View Project
Similar Project

Re-development of KTC Bus Stand at Bicholim, Goa

View Project
Similar Project

Construction of four lane bridge at Sanguem Town.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.