Project Duration
Stipulated Date of Commencement
March 01 2015
Stipulated Date of Completion /
Likely Date of Completion April 29 2015
Likely Date of Completion April 29 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 690,644.00
Awarded for
₹ 724,260.00
Project highlights
Miscellaneous HT Tapping works
Contractors
M/s. Ohm Engineers Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.