Project Duration
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 65,826,712.00
Project highlights
Office building for Directorate of Education with Offices, Cabins, Directorate room, Conference Room, etc. with beautifying landscape and parking.
Contractors
M/s. Ruby Realtors Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of new building for Directorate of Education at DIET Complex at Porvorim – Electrical works
completed
Status
Completed
Cost (₹)
Estimated at
₹ 4,043,826.00
Contractors
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works
View Project
Establishing Infrastructure for the Organic Waste Management Facility at Patto, Panaji – Balance works
View Project
Construction of Kala Bhavan at Sancoale- 11 KV HT Power Supply work.
View Project