Project Duration
Stipulated Date of Commencement
February 22 2024
Stipulated Date of Completion /
Likely Date of Completion August 21 2024
Likely Date of Completion August 21 2024
Status
10%
Completed
Cost (₹)
Estimated at
₹ 1,419,059.00
Awarded for
₹ 1,350,000.00
Project highlights
Diving Board Lift for Socorro Playground – Diving Pool
Contractors
M/s. Omega Elevators
Consultants
M/s. Banaji & Associates
See Similar Projects
Construction Of Multipurpose Hall Having Badminton Court, Gymnasium, Changing Room and Other Facilities at Socorro Ground. – Mechanical, Electrical, Plumbing scope of work pertaining to Lap Pool, Diving Pool and Baby Pool.
View Project
Construction of New Lecture Hall (1, 2 &3) at Goa Medical College and Hospital at Bambolim, Goa– Civil, Plumbing, Electrical, Lifts, HVAC and Firefighting works.
View Project
Demolition and reconstruction of Margao Government Industrial Training Institute and Government Multipurpose Higher Secondary School at Borda, Margao,Goa-Phase I.
View Project