Project Duration
Stipulated Date of Commencement February 27 2009
Stipulated Date of Completion /
Likely Date of Completion
August 26 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,541,225.00
Awarded for ₹ 10,902,411.00

Project highlights

Construction of retaining wall, compound wall and land filling etc.

 
Gallery Image
Contractors
M/s. Rohit Equipments
Gallery Image
Consultants
M/s. Banaji & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of sea wall and reinstatement of promenade near viewing deck opposite Dempo House in Panaji.

View Project
Similar Project

Restoration of Fonte Fenix, spring at Mala Panaji.

View Project
Similar Project

Air conditioning

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.