Project Duration
Actual Date of Completion November 06 2009
Status
100%
Completed

Project highlights

40 nos. Desktop Computers, 40 Nos. UPS, 40 Nos. MS-Office 2007 Software and 40 users Symantec Endpoint Protection 11.0 Antivirus Software

 
Contractors
M/s. City Computer Resources
Consultants
Inhouse
 