Project Duration
Stipulated Date of Commencement
May 05 2008
Actual Date of Completion
July 28 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,502,908.00
Awarded for
₹ 11,141,190.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.