Project Duration
Stipulated Date of Commencement
September 29 2013
Stipulated Date of Completion /
Likely Date of Completion March 28 2015
Likely Date of Completion March 28 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 145,763,468.00
Awarded for
₹ 158,936,223.00
Project highlights
• Total built-up area = 3610.63 sq. m.
• Ground Floor : Admin office, staff, etc.
• First Floor : 2 lecture halls.
• Second Floor : 1 lecture hall.
• Other facilities such as lift, fire fighting, HVAC, seat & desk with
self opening & closing system.
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 1 sub works. The details of the same available below
1
Furniture and Acoustical work.
100% completed
Project Duration
Stipulated Date of Commencement
May 22 2015
Stipulated Date of Completion /
Likely Date of Completion May 07 2015
Likely Date of Completion May 07 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,386,310.00
Awarded for
₹ 10,777,777.00
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Renovations of old IPHB Building to accommodate Goa Commission for Backward Classes
View Project
Air Conditioning work
View Project
Construction of IInd phase at Goa Dental College and Hospital at Bambolilm, Goa -Civil,Plumbing, internal electrical and fire fighting works-
View Project