Project Duration
Stipulated Date of Commencement
October 02 2019
Stipulated Date of Completion /
Likely Date of Completion November 01 2019
Likely Date of Completion November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 470,510.00
Awarded for
₹ 456,169.00
Project highlights
miscellaneous interior works.
Contractors
M/S.Creation Interior Contractor
Consultants
M/s. F P Project Management Pvt. Ltd.
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka- Package C (G.P.S Gaokarwada Mayem, G.P.S Shirodawadi Mulgao, G.P.S. Haturli Mayem)
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works in Bicholim Taluka- Package A-(G.P.S. Kahtar Dabdaba, G.P.S. Lamgao, G.P.S. Bagwada Pilgao, G.P.S. Mathwada Pilgao)
View Project
Upgradation/Renovation of Government College at Quepem, Goa -Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.
View Project