Project Duration
Stipulated Date of Commencement July 09 2010
Actual Date of Completion February 05 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,905,483.00
Awarded for ₹ 61,49,091.43.

Project highlights

Thework includes additional miscellaneous works such as roof covering for the open courtyards, security cabins, electrical panel room, additional water pump, etc. for the hostel building .

 
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Vijaykumar Sawant Associates
 