Project Duration
Stipulated Date of Commencement
October 18 2013
Stipulated Date of Completion /
Likely Date of Completion December 17 2013
Likely Date of Completion December 17 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,286,232.00
Awarded for
₹ 4,264,000.00
Contractors
M/s. Megastar Engineering
Consultants
In-house (GSIDC)