Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion April 14 2013
Likely Date of Completion April 14 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,872,528.00
Awarded for
₹ 1,872,528.00
Contractors
M/s. Technoworld
Consultants
In-house (GSIDC)