Project Duration
Stipulated Date of Commencement December 17 2012
Stipulated Date of Completion /
Likely Date of Completion
February 16 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,590,641.00
Awarded for ₹ 5,590,300.00
 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa

View Project
Similar Project

Maintenance/Renovation works of Community Health Centre at Valpoi . Maintenance Contract for 2 Nos lift of make M/s. Thyssenkrupp Elevators India for a period of three years.

View Project
Similar Project

Supply Installation Testing & Commissioning of water Heater & Purifier

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.