Project Duration
Stipulated Date of Commencement August 19 2010
Actual Date of Completion August 13 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 86,444,959.18
Awarded for ₹ 87,440,408.37
Final Cost of Project ₹ 185,200,470.00
 
Contractors
M/s. Ruby Realtors Pvt. Ltd., M/s. Ruby Realtors Pvt. Ltd.
Consultants
M/s. Effective Architectural Services, M/s. Effective Architectural Services
 