Project Duration
Stipulated Date of Commencement
August 19 2010
Actual Date of Completion
August 13 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 86,444,959.18
Awarded for
₹ 87,440,408.37
Final Cost of Project
₹ 185,200,470.00
Contractors
M/s. Ruby Realtors Pvt. Ltd., M/s. Ruby Realtors Pvt. Ltd.
Consultants
M/s. Effective Architectural Services, M/s. Effective Architectural Services