Project Duration
Stipulated Date of Commencement
March 05 2016
Actual Date of Completion
January 31 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 970,616,860.00
Awarded for
₹ 977,929,928.09
Final Cost of Project
₹ 100,845,718.00
Project highlights
Construction of new Jetty
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd
Consultants
M/s. Kuvelkar Salkar Associates