Project Duration
Stipulated Date of Commencement
July 10 2015
Actual Date of Completion
May 30 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rs. 33,55,777.00
Awarded for
₹ Rs. 41,44,116.80
Final Cost of Project
₹ 3,299,645.00
Project highlights
Box culvert work at Curchorem Goa.
Contractors
M/s. Aashirwad Constructions, Porvorim, M/s. Aashirwad Constructions, Porvorim
Consultants
M/s. Mahimtura Consultants Pvt. Ltd., M/s. Mahimtura Consultants Pvt. Ltd.