Project Duration
Stipulated Date of Commencement September 01 2007
Stipulated Date of Completion /
Likely Date of Completion
November 15 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,221,765.00
Awarded for ₹ 16,545,265.00
 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Extension of R.M.Os Hostel at Goa Medical College and Hospital, Bambolim, Goa – Sewage Treatment Plant

View Project
Similar Project

Supply, installation, testing and commissioning of 15 passenger cum bed lift for T. B. and chest diseases hospital, St. Inez, Goa.

View Project
Similar Project

Construction of 450 bedded Ward Block at GMC Complex, Bambolim, Goa. Civil, Plumbing, Electrical and Fire Fighting work.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.