Project Duration
Stipulated Date of Commencement
October 15 2006
Stipulated Date of Completion /
Likely Date of Completion July 14 2007
Likely Date of Completion July 14 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,627,955.00
Awarded for
₹ 15,186,060.00
Contractors
M/s. Friends Engineering Corporation
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.