Project Duration
Stipulated Date of Commencement December 17 2008
Actual Date of Completion January 31 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 263,660.00
Awarded for ₹ 392,000.00
 
Contractors
M/s. Oman Electricals
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 