Project Duration
Start Date 16/11/2004
End Date 30/11/2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 193,706,474.14
Awarded for ₹ 222,159,919.70

Project highlights

A 3-storeyed building with basement, ground + 2 floors with a plot area of 25,811 sq. m and built-up area of 19,310 sq. m. with a capacity of 230 beds
Main Building – Basement floor consists of car parking area for about 88 cars, waste disposal unit, AC plant, CSSD.- Another car parking area for 142 cars is around the main building. – Ground Floor consists of OPD clinics for gynaecologist / maternity, pediatrics, X-ray rooms, radiology department, ultra sound unit, 2 number of steel operation theaters and pharmacy, administrative section and conference room. First Floor consists of gymnasium, Accounts, ICU and ICCU, 8 steel operation theaters, etc. Second Floor consists of Wards and Blood Banks, etc. 4 hospital elevators, 2 passenger elevators, 2 service elevators
Ancillary Building (Service Block) – STP, mortuary, post-mortem, canteen, library, gas manifold, etc.
Building Management System and State-of-Art medical equipment’s (HVAC, elevators, fire fighting, external electrical work, medical gas pipelines, central sterile supply department, steel operation theater, mortuary cabinet, interior works, fire alarm & detection system and computerization), diagnostic equipment’s (imaging, pathology, medical diagnostic), minor surgical equipment’s, shadowless lamps & hydraulic tables for Operation Theater, kitchen equipment’s, hospital furniture including ambulance, geysers & incinerators, 33 KV cabling.

 
Contractors
M/s. Unity Infraprojects Limited
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 

Additional Work

This project involved 25 additional tasks. The details of the same available below

Status Progress Project Duration
Start Date / End Date
Cost (Rs.)
Estimated / Awarded
Consultants & Contractors
1 Interior works
100% completed
 
 

30/06/2007 - 11/30/2008

 

₹ 19,289,000.00 / ₹ 20,999,732.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Damian de Goa -
2 Supplying Installation Testing & Commissioning of 33 KV VCB Isolation at Substation for Electrical Supply.
100% completed
 
 

21/06/2008 - 20/09/2008

 

₹ 1,783,101.00 / ₹ 1,872,218.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Ohm Engineers & Electricals Pvt. Ltd. -
3 Supply Installation Testing & Commissioning of shadowless lamps, electro / mech hydraulic tables, etc. for Operation Theatre.
100% completed
 
 

26/04/2008 - 30/10/2008

 

₹ 28,378,896.00 / ₹ 26,653,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Genuine Medica Pvt. Ltd. -
4 Supply Installation Testing & Commissioning of Bio Medical Equipment (Part III) CT Scan.
100% completed
 
 

06/11/2008 - 05/01/2009

 

₹ 2,57,50,000.00 / ₹ 2,43,34,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Wipro GE Healthcare -
5 Supply Installation Testing & Commissioning of Bio Medical Equipment (Part II) Colour doppler & Ultra Sonography.
100% completed
 
 

06/11/2008 - 17/02/2009

 

₹ 43,00,000.00 / ₹ 38,00,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Siemens Ltd. -
6 Supply Installation Testing & Commissioning of water Heater & Purifier
100% completed
 
 

17/12/2008 - 31/01/2009

 

₹ 263,660.00 / ₹ 392,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Oman Electricals -
7 Supply, Installation, Testing & Commissioning of Medical Diagnostic.
100% completed
 
 

17/12/1008 - 19/03/2009

 

₹ 12,15,500.00 / ₹ 1,210,124.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Medraid Systems -
8 Supply Installation Testing & Commissioning of incinerators.
100% completed
 
 

15/01/2009 - 14/03/2009

 

₹ 8,43,750.00 / ₹ 885,937.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Don Whitley Scientific Equipments Pvt. Ltd. -
9 Supply, Installation, Testing and Commissioning of computer network with hardware and software.
100% completed
 
 

04/10/2007 - 30/06/2009

 

₹ 8,314,729.00 / ₹ 8,015,705.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Paradyne Infotech Limited -
10 Elevators.
100% completed
 
 

02/10/2006 - 30/09/2008

 

₹ 14,654,000.00 / ₹ 13,017,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Thyssenkrupp Elevators India Pvt. Ltd. -
11 Electrical works (External)
100% completed
 
 

15/10/2006 - 30/09/2008

 

₹ 15,627,955.00 / ₹ 15,186,060.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Friends Engineering Corporation -
12 Supplying and laying of 33 KV underground cable from Sub Station to District Hospital at Mapusa
100% completed
 
 

01/09/2007 - 30/09/2008

 

₹ 15,221,765.00 / ₹ 16,545,265.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Goa Friends Engineering & Electricals Pvt. Ltd. -
13 Air Conditioning and Ventilation System
100% completed
 
 

25/01/2007 - 15/12/2008

 

₹ 29,518,019.00 / ₹ 31,090,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Vigneshwar Air Conditioning Pvt. Ltd. -
14 Fire Fighting works.
100% completed
 
 

17/11/2006 - 30/09/2008

 

₹ 8,027,620.00 / ₹ 7,385,712.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Japsin Jacob Wire Drawing Pvt. Ltd. -
15 Bio medical equipment
100% completed
 
 

-

 

₹ / ₹

  M/s. Consulting Engineering Services Pvt. Ltd.
Bio medical equipment -
16 Steel Operation Theatre.
100% completed
 
 

26/03/2007 - 30/09/2008

 

₹ 17,671,482.00 / ₹ 18,007,783.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. MGI (I) Pvt. Ltd. -
17 Mortuary Cabinet.
100% completed
 
 

26/03/2007 - 05/10/2008

 

₹ 1,196,784.00 / ₹ 1,185,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Blue Star Ltd. -
18 Medical gases & vacuum plant.
100% completed
 
 

26/03/2007 - 30/09/2008

 

₹ 9,488,696.00 / ₹ 8,161,350.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. MGI (I) Pvt. Ltd. -
19 Central Sterile Supply Department.
100% completed
 
 

26/03/2007 - 24/06/2008

 

₹ 8,548,209.00 / ₹ 9,552,600.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. NAT Steel Equipment -
20 Supply, installation, testing, commissioning of fire detection and alarm system
100% completed
 
 

04/10/2007 - 30/09/2008

 

₹ 6,176,740.00 / ₹ 5,189,889.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Japsin Jacob Wire Drawing Pvt. Ltd. -
21 Supply Installation Testing & Commissioning of Hospital Furniture.
100% completed
 
 

26/04/2008 - 28/01/2009

 

₹ / ₹ 11,258,858.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Royal Safe Company -
22 Supply Installation Testing & Commissioning of Geysers & Water Purifiers.
100% completed
 
 

19/12/2008 - 01/02/2009

 

₹ 263,660.00 / ₹ 392,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Oman Enterprises -
23 Construction of soak pits.
100% completed
 
 

13/01/2009 - 19/03/2009

 

₹ 360,532.00 / ₹ 378,460.00

  Inhouse
M/s. C. Abdullah -
24 Water Cooler.
100% completed
 
 

- 21/11/2008

 

₹ / ₹ 205,956.00

  Inhouse
M/s. Blue Star Ltd. -
25 Supply Installation Testing & Commissioning of Bio Medical Equipment ( Part I ) Mobile X-Ray, C-Arm, CR-System.
100% completed
 
 

18/08/2009 - 19/01/2010

 

₹ 5,750,000.00 / ₹ 5,300,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
M/s. Jindal Photo Ltd. -

See Similar Projects

Face-lift to Tisk Usgao Hospital building including staff quarters

View Project

Construction of 500 Bedded District Hospital at Margao, Goa.– Supply, Installation, Testing and Commissioning of Token System

View Project

Construction of District Hospital at Mapusa, Goa

View Project
x