The existing health care facilities provided by Government of Goa is adequate, but it needs strengthening in terms of facilities and services. The present District Hospital in North Goa (Asilo Hospital) is about 50 years old, with 190 beds and upgrading of the existing hospital is almost impossible. Therefore, it is planned to build a new District Hospital at Mapusa with modern hospital concept and design having requisite facilities for secondary health care.
A 3-storeyed building with basement, ground + 2 floors with a plot area of 25,811 sq. m and built-up area of 19,310 sq. m. with a capacity of 230 beds
Main Building – Basement floor consists of car parking area for about 88 cars, waste disposal unit, AC plant, CSSD.- Another car parking area for 142 cars is around the main building. – Ground Floor consists of OPD clinics for gynaecologist / maternity, pediatrics, X-ray rooms, radiology department, ultra sound unit, 2 number of steel operation theaters and pharmacy, administrative section and conference room. First Floor consists of gymnasium, Accounts, ICU and ICCU, 8 steel operation theaters, etc. Second Floor consists of Wards and Blood Banks, etc. 4 hospital elevators, 2 passenger elevators, 2 service elevators
Ancillary Building (Service Block) – STP, mortuary, post-mortem, canteen, library, gas manifold, etc.
Building Management System and State-of-Art medical equipment’s (HVAC, elevators, fire fighting, external electrical work, medical gas pipelines, central sterile supply department, steel operation theater, mortuary cabinet, interior works, fire alarm & detection system and computerization), diagnostic equipment’s (imaging, pathology, medical diagnostic), minor surgical equipment’s, shadowless lamps & hydraulic tables for Operation Theater, kitchen equipment’s, hospital furniture including ambulance, geysers & incinerators, 33 KV cabling.
Project highlights
DESIGN CONCEPT
- District Level Hospital consisting of Basement, Ground and Two Floors.
- Design concept includes two courtyards for providing adequate light and ventilation.
- Well planned to co-relate all the Departments and adequate space made available for services and visitors.
- Provision of 8 Nos. elevators (6 Nos. – Public, 2 Nos. – Hospital lift for patients) and eight staircases for easy inter departmental movement.
- Fresh Water Supply of approx. 300 cum / day for hospital use.
- Electric sub-station of 230 V transformer – 2 Nos. with back up power for emergency services.
- Sewage Treatment Plant of 125 cum / day – treated water to be used for landscaping and flushing.
- Two wheeler parking – 75 Nos., four wheeler – 140 Nos. (Basement – 100 Nos., Open space – 40 Nos.)
HOSPITAL INFRASTRUCTURE FACILITIES BASEMENT (AREA – 5363.70 m2)
- Parking – 100 cars for hospital staff and Doctors.
- Utility services like HVAC, Electric room.
GROUND FLOOR (AREA – 4990.34 m2)
- OPD Clinics, Tests labs, Maternity / Delivery Section with provision of Operation Theater.
- C. T. Scan, X-rays, Ultrasound room, Radiologists room.
- Casualty ward, Blood Bank, Provision of Pharmacy.
FIRST FLOOR (AREA – 4925.41 m2)
- ICU (Intensive Care Unit), ICCU (Intensive Cardiac Care Unit)
- Operation Theatres – 4 Nos. with complete support facilities.
- Physiotherapy, Gymnasium, Maternity Wards – Beds (32 Nos.)
- Dialysis Room, Administration, Doctors and Consultants area.
SECOND FLOOR (AREA – 4963.53 m2)
- IPD (In Patient Departments), General Wards – Beds (182 Nos.) and Special Wards – Pay Beds (16 Nos.)
- Dental Clinic, Audiometric Clinic, Ophthalmic Clinic, Pediatric Clinic.
SEPARATE BLOCKS
- For Mortuary, Cafeteria and Laundry.
Location
Taluka: Bardez

Consultants
Additional Work
This project involved 22 additional tasks. The details of the same available below
Status | Progress | Project Duration Start Date / End Date |
Cost (Rs.) Estimated / Awarded Final Cost of Project |
Consultants & Contractors | ||
---|---|---|---|---|---|---|
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Mar 27 2007 - Sep 30 2008 |
/ 18,007,783.00 |
M/s. MGI (India) Pvt. Ltd. |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Mar 27 2007 - Oct 05 2008 |
/ 11,85,000.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
- Mar 20 2009 |
/ 81,61,350.00 |
M/s. MGI (India) Pvt. Ltd. |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Mar 27 2007 - Jun 24 2008 |
/ 95,52,600.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Jun 29 2007 - Nov 30 2008 |
/ 20,999,732.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Oct 05 2007 - Jun 30 2009 |
/ 80,15,705.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Aug 31 2007 - Sep 20 2008 |
/ 1,65,45,265.00 |
M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Oct 05 2007 - Sep 30 2008 |
/ 51,89,889.00 |
M/s. Japsin Jacob Wire Drawing Pvt. Ltd. |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Nov 17 2006 - Sep 30 2008 |
/ 73,85,712.00 |
M/s. Japsin Jacob Wire Drawing Pvt. Ltd. |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Jan 25 2007 - Dec 15 2008 |
/ 31,090,000.00 |
M/s. Vigneshwar Air Conditioning Pvt. Ltd. |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Oct 14 2006 - Sep 30 2008 |
/ 1,51,86,060.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Oct 02 2006 - Sep 30 2008 |
/ 1,30,17,000.00 |
M/s. ThyssenKrupp Elevator (India) Pvt. Ltd. |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Jun 21 2008 - Sep 20 2008 |
/ 18,72,218.00 |
M/s. Ohm Engineers & Electricals Pvt. Ltd. |
||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Dec 19 2008 - Feb 01 2009 |
/ 3,92,000.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Nov 06 2008 - Jan 05 2009 |
/ 2,43,34,000.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Oct 20 2008 - Nov 21 2008 |
/ 2,05,956.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Jan 15 2009 - Mar 14 2009 |
/ 8,85,937.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Jan 19 2009 - Mar 19 2009 |
/ 12,10,124.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Apr 20 2008 - Jan 28 2009 |
/ 1,12,58,858.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Nov 06 2008 - Feb 17 2009 |
/ 38,00,000.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Apr 26 2008 - Oct 30 2008 |
/ 2,66,53,000.00 |
|||
|
||||||
As on Mar 27 2015
Complete |
As on Mar 27 2015
100% completed
|
Aug 18 2009 - Nov 30 2009 |
/ 53,00,000.00 |
|||

See Similar Projects

Demolition and reconstruction of 220 bedded hospital in place of Public Health Center (I. D. Hospital) at Sadar Ponda Goa
View Project
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa.
View Project
Construction of building with compound wall for 30 bedded hospital at Bicholim.
View Project