Project Duration
Start Date 16/11/2004
End Date 30/11/2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 193,706,474.14
Awarded for ₹ 222,159,919.70

Project highlights

A 3-storeyed building with basement, ground + 2 floors with a plot area of 25,811 sq. m and built-up area of 19,310 sq. m. with a capacity of 230 beds
Main Building – Basement floor consists of car parking area for about 88 cars, waste disposal unit, AC plant, CSSD.- Another car parking area for 142 cars is around the main building. – Ground Floor consists of OPD clinics for gynaecologist / maternity, pediatrics, X-ray rooms, radiology department, ultra sound unit, 2 number of steel operation theaters and pharmacy, administrative section and conference room. First Floor consists of gymnasium, Accounts, ICU and ICCU, 8 steel operation theaters, etc. Second Floor consists of Wards and Blood Banks, etc. 4 hospital elevators, 2 passenger elevators, 2 service elevators
Ancillary Building (Service Block) – STP, mortuary, post-mortem, canteen, library, gas manifold, etc.
Building Management System and State-of-Art medical equipment’s (HVAC, elevators, fire fighting, external electrical work, medical gas pipelines, central sterile supply department, steel operation theater, mortuary cabinet, interior works, fire alarm & detection system and computerization), diagnostic equipment’s (imaging, pathology, medical diagnostic), minor surgical equipment’s, shadowless lamps & hydraulic tables for Operation Theater, kitchen equipment’s, hospital furniture including ambulance, geysers & incinerators, 33 KV cabling.

 
Contractors
M/s. Unity Infraprojects Limited
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 

Additional Work

This project involved 25 additional tasks. The details of the same available below

Status Progress Project Duration
Start Date / End Date
Cost (Rs.)
Estimated / Awarded
Consultants & Contractors
1 Interior works
100% completed
 
 

30/06/2007 - 11/30/2008

 

₹ 19,289,000.00 / ₹ 20,999,732.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Damian de Goa
2 Supplying Installation Testing & Commissioning of 33 KV VCB Isolation at Substation for Electrical Supply.
100% completed
 
 

21/06/2008 - 20/09/2008

 

₹ 1,783,101.00 / ₹ 1,872,218.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Ohm Engineers & Electricals Pvt. Ltd.
3 Supply Installation Testing & Commissioning of shadowless lamps, electro / mech hydraulic tables, etc. for Operation Theatre.
100% completed
 
 

26/04/2008 - 30/10/2008

 

₹ 28,378,896.00 / ₹ 26,653,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Genuine Medica Pvt. Ltd.
4 Supply Installation Testing & Commissioning of Bio Medical Equipment (Part III) CT Scan.
100% completed
 
 

06/11/2008 - 05/01/2009

 

₹ 2,57,50,000.00 / ₹ 2,43,34,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Wipro GE Healthcare
5 Supply Installation Testing & Commissioning of Bio Medical Equipment (Part II) Colour doppler & Ultra Sonography.
100% completed
 
 

06/11/2008 - 17/02/2009

 

₹ 43,00,000.00 / ₹ 38,00,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Siemens Ltd.
6 Supply Installation Testing & Commissioning of water Heater & Purifier
100% completed
 
 

17/12/2008 - 31/01/2009

 

₹ 263,660.00 / ₹ 392,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Oman Electricals
7 Supply, Installation, Testing & Commissioning of Medical Diagnostic.
100% completed
 
 

17/12/1008 - 19/03/2009

 

₹ 12,15,500.00 / ₹ 1,210,124.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Medraid Systems
8 Supply Installation Testing & Commissioning of incinerators.
100% completed
 
 

15/01/2009 - 14/03/2009

 

₹ 8,43,750.00 / ₹ 885,937.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Don Whitley Scientific Equipments Pvt. Ltd.
9 Supply, Installation, Testing and Commissioning of computer network with hardware and software.
100% completed
 
 

04/10/2007 - 30/06/2009

 

₹ 8,314,729.00 / ₹ 8,015,705.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Paradyne Infotech Limited
10 Elevators.
100% completed
 
 

02/10/2006 - 30/09/2008

 

₹ 14,654,000.00 / ₹ 13,017,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Thyssenkrupp Elevators India Pvt. Ltd.
11 Electrical works (External)
100% completed
 
 

15/10/2006 - 30/09/2008

 

₹ 15,627,955.00 / ₹ 15,186,060.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Friends Engineering Corporation
12 Supplying and laying of 33 KV underground cable from Sub Station to District Hospital at Mapusa
100% completed
 
 

01/09/2007 - 30/09/2008

 

₹ 15,221,765.00 / ₹ 16,545,265.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
13 Air Conditioning and Ventilation System
100% completed
 
 

25/01/2007 - 15/12/2008

 

₹ 29,518,019.00 / ₹ 31,090,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Vigneshwar Air Conditioning Pvt. Ltd.
14 Fire Fighting works.
100% completed
 
 

17/11/2006 - 30/09/2008

 

₹ 8,027,620.00 / ₹ 7,385,712.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
15 Bio medical equipment
100% completed
 
 

-

 

₹ / ₹

  M/s. Consulting Engineering Services Pvt. Ltd.
- Bio medical equipment
16 Steel Operation Theatre.
100% completed
 
 

26/03/2007 - 30/09/2008

 

₹ 17,671,482.00 / ₹ 18,007,783.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. MGI (I) Pvt. Ltd.
17 Mortuary Cabinet.
100% completed
 
 

26/03/2007 - 05/10/2008

 

₹ 1,196,784.00 / ₹ 1,185,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Blue Star Ltd.
18 Medical gases & vacuum plant.
100% completed
 
 

26/03/2007 - 30/09/2008

 

₹ 9,488,696.00 / ₹ 8,161,350.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. MGI (I) Pvt. Ltd.
19 Central Sterile Supply Department.
100% completed
 
 

26/03/2007 - 24/06/2008

 

₹ 8,548,209.00 / ₹ 9,552,600.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. NAT Steel Equipment
20 Supply, installation, testing, commissioning of fire detection and alarm system
100% completed
 
 

04/10/2007 - 30/09/2008

 

₹ 6,176,740.00 / ₹ 5,189,889.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
21 Supply Installation Testing & Commissioning of Hospital Furniture.
100% completed
 
 

26/04/2008 - 28/01/2009

 

₹ / ₹ 11,258,858.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Royal Safe Company
22 Supply Installation Testing & Commissioning of Geysers & Water Purifiers.
100% completed
 
 

19/12/2008 - 01/02/2009

 

₹ 263,660.00 / ₹ 392,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Oman Enterprises
23 Construction of soak pits.
100% completed
 
 

13/01/2009 - 19/03/2009

 

₹ 360,532.00 / ₹ 378,460.00

  Inhouse
- M/s. C. Abdullah
24 Water Cooler.
100% completed
 
 

- 21/11/2008

 

₹ / ₹ 205,956.00

  Inhouse
- M/s. Blue Star Ltd.
25 Supply Installation Testing & Commissioning of Bio Medical Equipment ( Part I ) Mobile X-Ray, C-Arm, CR-System.
100% completed
 
 

18/08/2009 - 19/01/2010

 

₹ 5,750,000.00 / ₹ 5,300,000.00

  M/s. Consulting Engineering Services Pvt. Ltd.
- M/s. Jindal Photo Ltd.

See Similar Projects

Construction of Yatri Niwas at GMC Complex, Bambolim, Goa-Civil, Plumbing & Internal Electrical works

View Project