Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,729,540.00
Awarded for ₹ 27,700,000.00
 
Gallery Image
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Gallery Image
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation/alteration of DIET Building for Goa Human Resource Development Corporation at Porvorim, Goa

View Project
Similar Project

Construction STP Sanquelim – Compound Wall & Allied work.

View Project
Similar Project

Interior work for TCP branch office, Tiswadi Branch, 5th Floor, Kamat Towers

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.